Work on site has commenced which is off the scale exciting!! The next couple of weeks will be all about preparing the site, we need to have 550m2 of hard standing laid, so not exactly sure when holes will be dug or things actually built. We do have a digger on site now so hopefully not too long.
As well as laying hardcore, the roof of the Stables has also had its stinky asbestos roof removed by some specialist sub-contractors. This was to make the site safe for normal work although as is often the way, it has now exposed unsafe roof timbers so I’m not exactly sure yet whether that’s a win or not …